I called Kashyap at the site office this Monday. He was not aware about the status on the CC, and has completely gone back on their earlier update of awaiting for the CC. He mentioned clearly that he has no clear visibility on the date of receiving the CC. On further proding he asked me to get in touch with Mr.Anand Almedia at the HDIL Main Office in Bandra(E). I have tried reaching out to Mr.Anand at 02267888000, but have not been able to till now. Please let me know if anyone has luck in speaking to this person. PS: Further when I enquired with Kashyap abt the work going on the in the adjacent plot, he mentioned that the work is executed by HDIL and it is for constructing a building meant for rehabilitating the existing tenants of the house which were existing on these plots. I called Kashyap at the site office this Monday. He was not aware about the status on the CC, and has completely gone back on their earlier update of awaiting for the CC. He mentioned clearly that he has no clear visibility on the date of receiving the CC. On further proding he asked me to get in touch with Mr.Anand Almedia at the HDIL Main Office in Bandra(E). I have tried reaching out to Mr.Anand at 02267888000, but have not been able to till now. Please let me know if anyone has luck in speaking to this person. PS: Further when I enquired with Kashyap abt the work going on the in the adjacent plot, he mentioned that the work is executed by HDIL and it is for constructing a building meant for rehabilitating the existing tenants of the house which were existing on these plots.
As already mentioned in the mail sent by Abhinav to the group, 1. we had a discussion between the 10 of us who came for the meeting at Inorbit mall, and later on we went to the site office. 2. We spoke to Kashyap but we got the usual response from him to our queries about the CC and the commencement of work at the site. Later on we requested Kashyap to call Mr.Anand Almedia (AGM) and all the attendees spoke to him on speaker phone. 3. Anand did not give us any firm response but has agreed to meet us in person at the HDIL Meadows site office on 8th Dec at 11:30 AM. 4. Our strength in numbers present at the meeting did impact the attitude of HDIL site office people. They had to sit up and take notice. 5. Hence, please solemnly request all the people who have booked their flats in Meadows to be present for this crucial meeting. Once again the meeting is scheduled on 8th Dec at 11:30 AM at HDIL Meadows Site Office. As already mentioned in the mail sent by Abhinav to the group, 1. we had a discussion between the 10 of us who came for the meeting at Inorbit mall, and later on we went to the site office. 2. We spoke to Kashyap but we got the usual response from him to our queries about the CC and the commencement of work at the site. Later on we requested Kashyap to call Mr.Anand Almedia (AGM) and all the attendees spoke to him on speaker phone. 3. Anand did not give us any firm response but has agreed to meet us in person at the HDIL Meadows site office on 8th Dec at 11:30 AM. 4. Our strength in numbers present at the meeting did impact the attitude of HDIL site office people. They had to sit up and take notice. 5. Hence, please solemnly request all the people who have booked their flats in Meadows to be present for this crucial meeting. Once again the meeting is scheduled on 8th Dec at 11:30 AM at HDIL Meadows Site Office.
Seems like I am also in the same boat. Had booked the flat in F Wing back in Nov 2010, but in the past few months there has been no update from the Site Office. Every time I call, I have been told that they have got the verbal commitmment and that they are currently awaiting the formal CC from BMC. Please keep me in the loop regarding any next steps you guys plan to take. Its high time we take an action. P.S:Incidentally in the plot adjoining this one, the work is in full swing, I recently saw a crane being installed there!Seems like I am also in the same boat. Had booked the flat in F Wing back in Nov 2010, but in the past few months there has been no update from the Site Office. Every time I call, I have been told that they have got the verbal commitmment and that they are currently awaiting the formal CC from BMC. Please keep me in the loop regarding any next steps you guys plan to take. Its high time we take an action. P.S:Incidentally in the plot adjoining this one, the work is in full swing, I recently saw a crane being installed there!
Ask a Question
120 Characters Left





    Trending Categories

    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!