Q:
I have booked in Casa rio Genevia/A, and promised to give positioned in 2013. still waiting. now the new date is Dec 14... anyone who has booked a flat in CASA RIO GENEVIA???
Dear Mr.Dinesh,
I also booked a flat in Geneview A and now have received a demand letter with enormous charges that I should pay before the possession (for fit outs) from Lodha. I am surprised to see that they are demanding Rs.76,080 as Civic Governance Charges. I understand that the cost of all common areas and facilities are loaded on rates and also in difference of built up area and actual carpet area. I am not aware about this high charges of Governance charges to be paid by customer before the possession and for the entire period of construction.
Also, the other rates are very high :
1) Legal Charges : Rs.20,000 (for what?)
2) Water & Electrical connection : Rs.40,000
3) Power Infrastructure : Rs.8000 (What is this?)
4) Club membership Fee : Rs.7000 (why before possession ?)
I am sure, you must have got a similar letter. What are you doing about it? Please advise me about the applicable rules and laws.
Regards,
Dixit
meet.dixitvs@gmail.com
Good to know that sooner or letter we all will be staying in the same building Genevia A. is there any communication regarding the fit - out possession? thanks..
29th January 2015
Hi Dixitji, please ping me on my whats app at to add you in the genevia group.
6th April 2015
Hi,
I am planning to buy a flats in Casa Rio. But i am little bit confused about the project. Is Genevia a tower in Casa Rio? How many towers are there in Casa Rio? What is it's current price and how much i have to pay as a booking amount? Can anybody update me about it's detail?
Hi Shantanu,
Yes Genevia is a tower in Lodha Casa Rio Project. there are many towers in the same project i dont know exact number of tower. you can reach to sales office for the price details.
29th January 2015
hi snehil,
I have created a whats app group for Genevia. please ping me on so that i can add you in the group.
6th April 2015
Dear Flat owners of Genevieve Block A,
We have been called for handing over of our flat. However, Lodha want us to sign a document that says that we have been provided the Flat along with all the fit up as per the agreement and we shall not be having any claim on builder of any nature in future. They have mention that customer shall check the flat and inform the discrepancies if any and the same shall be corrected by the builder within 30 days. They want us to sign this document at their HO in Mahalaxmi and after that only they shall provide us the keys.
It is also to be noted that OC is not yet obtained and as per the builder it may take 7 months from now. whereas customers need to pay for all maintenance charges from now.
This is not fair. I seek advise from other residents please. Please share your experience if any one of you have already get the keys and whether you also get it through the same process.
Regards,
Dixit
Dear Mr Dixit,
I got a fit-out demand letter
16th February 2015
Dear Mr. Dixit,
Can you call me at 9920909190
16th February 2015
I am from Genevia C the date given to me Feb 2015 actual agreement date is Feb 2013. So did you ask if he is delivering flat in December 2014 for Genevia A?
The latest tentative time given is 10 to 15 days...:)
29th January 2015