Chandan Kumar Singh, Apartment Resident
Q: The construction seems to have been halted at the moment. There is some concern regarding their approvals from GDA. My bank, which had earlier approved my loan has now put it on hold because of some FSI transfer issues.

My replies to this discussion
Well, here are the details. The project actually started off as Ansal's Aquapolis. There are several towers, most of which are being developed by Ansal. A couple of towers, however, were being developed by Ansals and Lakshya jointly. I have invested in one of these towers. The agreement was made when this was the arrangement and my bank loan was approved without any hassle. Also, I had paid 25% of the amount at the beginning. After the loan was approved, I was expecting the next instalment order to come, but they did not send any such demand letter for 4-5 months. Bank loans, I believe, remain valid for just 3 months after which you have to apply to them for approval once again.Well, here are the details. The project actually started off as Ansal's Aquapolis. There are several towers, most of which are being developed by Ansal. A couple of towers, however, were being developed by Ansals and Lakshya jointly. I have invested in one of these towers. The agreement was made when this was the arrangement and my bank loan was approved without any hassle. Also, I had paid 25% of the amount at the beginning. After the loan was approved, I was expecting the next instalment order to come, but they did not send any such demand letter for 4-5 months. Bank loans, I believe, remain valid for just 3 months after which you have to apply to them for approval once again.
So after 5 months when the demand letter arrived, i sent it to bank, and they re-initiated the process of approval. In the end they informed me that all was fine on my end, but in this time period it seems that Lakshya has taken over the full ownership of these towers. It's a case of FSI transfer. And the bank now needs the letters from board of directors and the official FSI transfer documents to go ahead with the loan. They said its not a problem, they just need the letters. I asked the builders and they also say that's not a problem and they will provide the letters. However, it is expected to take a month since the letters are still with the court and will take some time. In the meanwhile, they have promised no instalment will be demanded and no late payment or any other charges will be levied. Also they promised that construction is on full swing. I will personally verify that once i am back in Delhi at the end of this month.So after 5 months when the demand letter arrived, i sent it to bank, and they re-initiated the process of approval. In the end they informed me that all was fine on my end, but in this time period it seems that Lakshya has taken over the full ownership of these towers. It's a case of FSI transfer. And the bank now needs the letters from board of directors and the official FSI transfer documents to go ahead with the loan. They said its not a problem, they just need the letters. I asked the builders and they also say that's not a problem and they will provide the letters. However, it is expected to take a month since the letters are still with the court and will take some time. In the meanwhile, they have promised no instalment will be demanded and no late payment or any other charges will be levied. Also they promised that construction is on full swing. I will personally verify that once i am back in Delhi at the end of this month.
Update: All issues seem to hav been sorted out now. I got my loan approved from SBI yesterday and the latest demand paid out successfully. Work seems set to resume in a week's time. Possession date tentatively March 2016.Update: All issues seem to hav been sorted out now. I got my loan approved from SBI yesterday and the latest demand paid out successfully. Work seems set to resume in a week's time. Possession date tentatively March 2016.
It has been a year since I paid the registration fee and since then not a single letter of demand for installment has come from them. Upon enquiry, they keep saying that two banks (SBI and ICICI) have approved the project and they are waiting for the confirmation letter from them which should come in 10-15 days. I am waiting for this 10-15 day period to end since the last 5-6 months. The construction site wears a deserted look. They are saying that all the laborers have left (which is bound to happen since they had no money to them). The project will go ahead only after they start receiving installment money, which has not been happening for the last 1 year. In retrospect, seems like a HUGE mistake going with Lakshya. Should have opted for the Ansal's flats in the same township, which were costlier, but at least they are being developed in time.It has been a year since I paid the registration fee and since then not a single letter of demand for installment has come from them. Upon enquiry, they keep saying that two banks (SBI and ICICI) have approved the project and they are waiting for the confirmation letter from them which should come in 10-15 days. I am waiting for this 10-15 day period to end since the last 5-6 months. The construction site wears a deserted look. They are saying that all the laborers have left (which is bound to happen since they had no money to them). The project will go ahead only after they start receiving installment money, which has not been happening for the last 1 year. In retrospect, seems like a HUGE mistake going with Lakshya. Should have opted for the Ansal's flats in the same township, which were costlier, but at least they are being developed in time.
Hi Kuldeep... I am not really sure what's going on at the moment... The FSI transfer has been approved (I confirmed that via some internal sources some time back). I am not sure what the issue with the banks is at the moment. They said work will resume by August end, so let's see. Have you also invested in Lakshya?Hi Kuldeep... I am not really sure what's going on at the moment... The FSI transfer has been approved (I confirmed that via some internal sources some time back). I am not sure what the issue with the banks is at the moment. They said work will resume by August end, so let's see. Have you also invested in Lakshya?
Yes, its still the same... no progress whatsoever. Extremely frustrating.Yes, its still the same... no progress whatsoever. Extremely frustrating.
Every time I ask them they say everything is in order and that constructions will beging in the next 45-60 days... Almost 2 years have gone in this fashion. I wonder if it makes more sense to ask the money back and invest in something that's ready to move or on the verge of completion.Every time I ask them they say everything is in order and that constructions will beging in the next 45-60 days... Almost 2 years have gone in this fashion. I wonder if it makes more sense to ask the money back and invest in something that's ready to move or on the verge of completion.
Not sure if you are actually trying to make a selling here Mr. Manoj, but the construction is NOT going on. I visited the place again last week, and there is NO activity here. The guys, as usual, have set up a new deadline citing diwali and chhath celebrations due to which labor is not available. The only positive development in the last couple of years that has taken place is that they have at least initiated the loan processing formalities.Not sure if you are actually trying to make a selling here Mr. Manoj, but the construction is NOT going on. I visited the place again last week, and there is NO activity here. The guys, as usual, have set up a new deadline citing diwali and chhath celebrations due to which labor is not available. The only positive development in the last couple of years that has taken place is that they have at least initiated the loan processing formalities.
Mr. Manoj, it's not a matter of 15-20 months.. please stop spreading misinformation.. the construction has NOT BEEN GOING ON FOR THE PAST SEVERAL MONTHS. And this project is not by Ansal, we are discussing the "LAKSHYA AQUAPOLIS" here and I believe Ansal has transferred the FSI to Lakshya.Mr. Manoj, it's not a matter of 15-20 months.. please stop spreading misinformation.. the construction has NOT BEEN GOING ON FOR THE PAST SEVERAL MONTHS. And this project is not by Ansal, we are discussing the "LAKSHYA AQUAPOLIS" here and I believe Ansal has transferred the FSI to Lakshya.
Hi Kuldeep, received a mail from them about 10 days back saying the papers have been finalized and asking us to submit relevant docs for processing the loan. They are getting it done from SBI, thankfully. The mail also mentioned that construction is on "full swing" but i visited the place and couldn't find any "swing" at least until the last week...Hi Kuldeep, received a mail from them about 10 days back saying the papers have been finalized and asking us to submit relevant docs for processing the loan. They are getting it done from SBI, thankfully. The mail also mentioned that construction is on "full swing" but i visited the place and couldn't find any "swing" at least until the last week...
Hi Kuldeep, no progress yet. The construction is on a complete standstill. I keep visiting them, but the same response that it will resume in 15-20 days and never happens. It's the same with almost any builder in the whole of NCR. Frustrating.Hi Kuldeep, no progress yet. The construction is on a complete standstill. I keep visiting them, but the same response that it will resume in 15-20 days and never happens. It's the same with almost any builder in the whole of NCR. Frustrating.
Update: It appears that the pending issues have been resolved. SBI has approved the project and the loan process has started. I submitted the loan documents today. The construction might resume post Diwali. Will post any further update soon.Update: It appears that the pending issues have been resolved. SBI has approved the project and the loan process has started. I submitted the loan documents today. The construction might resume post Diwali. Will post any further update soon.
My comments to replies
Update: All issues seem to hav been sorted out now. I got my loan approved from SBI yesterday and the latest demand paid out successfully. Work seems set to resume in a week's time. Possession date tentatively March 2016.
Hi Kuldeep, yes, it's indeed good to see some development. Suraj: I am on the CLP plan. I believe this is still one of the better projects out there in this region. The design and overall open spaces will make for a pleasurable experience once the township is completely ready. There have been some delays but that's true for most ongoing projects these days. And in any case, it will still be some time before the are becomes completely habitable so the delay doesn't matter anyway. Sukhpreet: As of now, SBI is the only one associated with the project. But I am sure any other bank should be able to sanction the loan. Please do check out with them. I had my loan initially approved from DHFL (at the time of booking). Then the construction halted and my sanction expired. This time I applied with SBi and got approved very fast. In fact, if there isn't any specific reason for you to go with some other bank, I would recommend going with SBI.
18th November 2014
I suggest all of us who have invested/planning to invest in this project stay in touch. Please do add me up on whatsapp. Email me with your number at chandan.singh@gmail.com. I will create a whatsapp group and add you in there for future discussions.
18th November 2014

When ever I call the sales staff, they do not give any update about the project. It is very frustating. Even I'v visitd the site but not getting any update about D bocks. Construction halted for about 18 months. Any update? Suneel
Who did you speak to? Try speaking to Mr. Ashok over there.
18th November 2014

They called me 5 months back, they started the loan process from SBI and construction has started and in full swing. but nothing happened till yet.. bad luck booking with Lakshya. Even they are not telling the truth whats the actual problem.
Kuldeep jee, we have formed a WhatsApp group of people who have invested in Aquapolis. Please send me your contact number at chandansingh@gmail.com. Some of us have met recently and planning to visit the developers and see what we can do.
7th September 2015

Hey Guy's, Is there any update...Please share..
The construction is halted as of now. They say that the labourers have left. According to them work will resume in August. The delivery time is already delayed by 1 year. Feeling sorry to have invested in this project.
22nd July 2013

Dear residents, Is there any update on this, how is construction going on and what about FSI transfer.
hi kuldeep, am still waiting for the papers from their end... as far as construction is concerned, I will update the status on this weekend. I am visiting the site this Sunday.
9th January 2013

Hello Guy's, Any update on the construction, I don't see any progress since last two month Lakshya staff told me entire super structure will be completed by March-April 2016. and possession by March-April 2017. Please keep sharing on this forum.
Hello Kuldeep and Manish. I have some more people (those who have invested in the project) and we have been constantly following up with Lakshya. The project is an absolute disaster and we have made some decisions regarding the next steps. Please contact me on my email: chandan.singh@gmail.com or give me a call (or add on WhatsApp) at the following number: 8447892002, so that we can discuss further.
2nd October 2016
As a quick update, there is no chance that they will be able to provide the possession even by 2018/19. I have been constantly pressurizing them and have been sending them several notices. Even met their Director (Suraj Awana) a couple of weeks ago, who first assured (under pressure) a delivery by August 2017, and even agreed to give it to us in writing. But when I pressurized them to give it in writing he turned back on his words and lied outright saying that he meant December 2017. The real fact is that there are just 3-4 people working at the site (on random days) and there is absolutely no work happening since the last few years. To anyone else who is considerign investing in Lakshya Aquapolis, please note that Lakshya is a fraudster, and stay away from them. More than 4 years have elapsed since the promised delivery date and it looks like it will be another 3-4 years before they complete the project (IF they complete the project).
2nd October 2016
To add to the above comments, there is a whole chain of emails and videos that I will be making public very soon to show the fraudster and scamsters that Lakshya Realinfra are.
2nd October 2016

I m too waiting for my flat since 2011. Huge money blocked by Ansal AQUAPOLIS. G Singh 7042491436, 9868772851,
Do not ever invest with Lakshya Aquapolis. They are frauds. Check this review in detail here: http://lakshyarealinfrareview.com/
4th September 2018

Q: Hi, recently I have booked under-construct Villa project and taken home loan, but I am confused which option should I opt for EMI? Which one is better Pre-EMI or Full EMI?
My replies to this discussion
Hi, I opted for a full EMI for my house loan with SBI. I was supposed to get the possession in an year's time. But now I see the builder is delaying the project and it may be 3-4 years until possession. In the meanwhile it's going to be a problem for me to be paying both house rent and EMIs as well as for my child's education starting next year. Is it possible to switch from full EMI to pre EMI now? I have already been paying the full EMI for the past one year and the bank has disbused about 10 lakh so far.Hi, I opted for a full EMI for my house loan with SBI. I was supposed to get the possession in an year's time. But now I see the builder is delaying the project and it may be 3-4 years until possession. In the meanwhile it's going to be a problem for me to be paying both house rent and EMIs as well as for my child's education starting next year. Is it possible to switch from full EMI to pre EMI now? I have already been paying the full EMI for the past one year and the bank has disbused about 10 lakh so far.
Ask a Question
120 Characters Left





    Trending Categories

    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!