Vikas Dhall, Apartment Resident
Q: I want to know about all the approval status of this project. If this project is approved by GDA? do all the clearance taken.

My replies to this discussion
Forget everything - the possession has been delayed twice. It was supposed to be handed over by july 2014, then December 2014, now it is March 2015. And no compensation from builder.Forget everything - the possession has been delayed twice. It was supposed to be handed over by july 2014, then December 2014, now it is March 2015. And no compensation from builder.
Has anyone asked for monthly fine which is Rs 5 /Sqft? What is the promise made to you?Has anyone asked for monthly fine which is Rs 5 /Sqft? What is the promise made to you?
My comments to replies
Forget everything - the possession has been delayed twice. It was supposed to be handed over by july 2014, then December 2014, now it is March 2015. And no compensation from builder.
March they say.
15th December 2014

Has anyone asked for monthly fine which is Rs 5 /Sqft? What is the promise made to you?
Whats is the three month penalty?
15th December 2014