Q:
I have booked a flat in LDA srishti apartment flat Kursi rd scheme 3 years back. Can any one please tell me what is the status of project. LDA people even do not pick the phone.
Would pl any body let me now the details of consumer forum in Lucknow? I would be going to consumer court under the act mentioned by parul saxena. 3 years passed but ground work is yet to begun for Sulabh? Anybody willing to join me for going to consumer forum for compensation for the delay?Would pl any body let me now the details of consumer forum in Lucknow? I would be going to consumer court under the act mentioned by parul saxena. 3 years passed but ground work is yet to begun for Sulabh? Anybody willing to join me for going to consumer forum for compensation for the delay?
If you do not give full payment, LDA will charge interest on your remaining payment. If you make full payment your investment is dead. I have made full payment. What is the option out of this?If you do not give full payment, LDA will charge interest on your remaining payment. If you make full payment your investment is dead. I have made full payment. What is the option out of this?
Yesterday I visited Sulabh Awas Janakipuram. LDA has created a boundary wall around Sulabh Awas, Janakipuram. In Sulabh 2 BHK flat, tiles are laid in all rooms, bathrooms & balconies. Paint is also done outside buidling. By this time they should have given possession. Looking at the slow progress which I show yesterday, It will be another 8 to 10 months before actual possession starts. -Yesterday I visited Sulabh Awas Janakipuram. LDA has created a boundary wall around Sulabh Awas, Janakipuram. In Sulabh 2 BHK flat, tiles are laid in all rooms, bathrooms & balconies. Paint is also done outside buidling. By this time they should have given possession. Looking at the slow progress which I show yesterday, It will be another 8 to 10 months before actual possession starts. -
I have booked 2 BHK flat in Sulabh Awas near Shristi Appartments. Any update whether the work has started on this?I have booked 2 BHK flat in Sulabh Awas near Shristi Appartments. Any update whether the work has started on this?
I had filed an RTI query to Lucknow regarding status of Sulabh Awas Yojna Janakipuram. I got the reply from LDA that it will be handed after December, 2013. After I visited the site, I realised that 50% of the work is compled. It may take another two years for possession.I had filed an RTI query to Lucknow regarding status of Sulabh Awas Yojna Janakipuram. I got the reply from LDA that it will be handed after December, 2013. After I visited the site, I realised that 50% of the work is compled. It may take another two years for possession.
My comments to replies
Would pl any body let me now the details of consumer forum in Lucknow? I would be going to consumer court under the act mentioned by parul saxena. 3 years passed but ground work is yet to begun for Sulabh? Anybody willing to join me for going to consumer forum for compensation for the delay?
I am ready Parul madam. LDA will not listen to single person like me and you. Lets unite and fight LDA..
20th June 2013