Q: ANSAL API has launched Golf City in Lucknow with Paradise diamond and all of us who bought flats in the schme are being cheated by ansals.After paradise diamond many schemes were launched by them and they have started construction of the same much earlier,but i dont know that why they are not initiating construction of Paradise Diamond.Every time you ask their local office in Lucknow and you get a answer that in next 3 months it will start.More then one and half year is passed but still no construction has started.In contract they have mentioned that flats will be delivered in 36 months,but going by this pace i dont think that we can get the flats even in 60 months.I need a clearification from them about this pathetis status of thier flag ship launch of paradise diamond in lucknow.

My replies to this discussion
I visited the project side on 08/08/2013 and saw some foundation work of E ,F,G AND H blocks of PD-II. I also met staff of NCC at the project side and he assures that the building of PD-II will be completed in next two and half year. On the other hand I also received reply from LDA regarding map approval of Paradise Diamond under RTI ACT in which they refused to issue any map or permission to construct the PD, copy of which you may receive by contacting me at anilsahjwani@gmail.comI visited the project side on 08/08/2013 and saw some foundation work of E ,F,G AND H blocks of PD-II. I also met staff of NCC at the project side and he assures that the building of PD-II will be completed in next two and half year. On the other hand I also received reply from LDA regarding map approval of Paradise Diamond under RTI ACT in which they refused to issue any map or permission to construct the PD, copy of which you may receive by contacting me at anilsahjwani@gmail.com
Thanks Mr. Mohan Singh Bohra ji for latest information I visited the webpage of LDA and found that map was applied on 09.03.2010 and Permit date is 20.09.2010 and permit no is 31517. The date of PERMIT is much more earlier and how it was not received by Ansal Api ?Thanks Mr. Mohan Singh Bohra ji for latest information I visited the webpage of LDA and found that map was applied on 09.03.2010 and Permit date is 20.09.2010 and permit no is 31517. The date of PERMIT is much more earlier and how it was not received by Ansal Api ?
I got mail from Manoj Agawal of Ansal API as below. Refer to your trail mail, we would like to inform you that L.D.A. released map is yet awaited. However, we are in receipt of technical approval & we are in compliance with construction norms for the project. Regards, Manoj AgarwalI got mail from Manoj Agawal of Ansal API as below. Refer to your trail mail, we would like to inform you that L.D.A. released map is yet awaited. However, we are in receipt of technical approval & we are in compliance with construction norms for the project. Regards, Manoj Agarwal
Today I talked to Ansal and they are saying that work will start in April'2014. Dear Arun Sahu ji which type of construction you saw at site, please inform us.Today I talked to Ansal and they are saying that work will start in April'2014. Dear Arun Sahu ji which type of construction you saw at site, please inform us.
Any development at site ?Any development at site ?
Kanika ji actually I applied for PD II under RTI act but the LDA authorities not clearly mentioned the PDI or PDII .I again applied for clarification under RTI act along with copy of approved map list as provided by LDA website in which it is mentioned that map of PD-II sanctioned on 20.09.2010 under permit no 31517.Kanika ji actually I applied for PD II under RTI act but the LDA authorities not clearly mentioned the PDI or PDII .I again applied for clarification under RTI act along with copy of approved map list as provided by LDA website in which it is mentioned that map of PD-II sanctioned on 20.09.2010 under permit no 31517.
My comments to replies
For kind information, permission is granted in june,2013 but with retrospective effect.It is mendatory to accept or reject map approval within 6-7 months from the date of application. If it is not rejected then it is deemed to be accepted/granted permission. LDA can only delay in issuing it. one reason that i see may be that LDA is facing so may litigations with Ansal api which may result in delay in map approvals.
On LDA webpage by entering the application no 36421(which is for PD-2) in MAP status I found as below. Applicant Detail Applicant Name ANSAL PROP & INFRA LTD Address Y M C A BUILDING, 13 RANA PRATAP MARG LUCKNOW Property Number 1 Entry Date 09/03/2010 Status Detail Date Status Remark 19/07/2011 05:09:56 PM T 19/07/2011 05:12:12 PM S TECH.COMM. DATED.20/09/2010 Challan Detail Deposit Date Bank Amount 18/03/2009 UCO BANK 4953000.00 02/05/2009 UCO BANK 8711000.00 09/03/2010 UCO BANK 225440.00 15/07/2011 UCO BANK 136500.00
9th July 2013

Notice for PD-2. Ansal has started issuing final call notice for PD-2. In case u fail to pay within a fortnight, u may face cancellation. I have got disbursed through PNB.
Bohra ji PNB financing without getting map approval from LDA?
26th July 2013

PNB is releasing on the basis of technical approval that ansal has got.
Bohra ji it means that it is verified that they have technical approval from LDA and we will hope of getting flats from Ansal API