Right now there is no project in NOida where in you could get rate of Approx 3500 Rs per square feet Basic and we all invested here in the same rate bracket.........Now they are seeing this as gold mine because everywhere rates are approx Rs 4200 per sq ft basic rate .....They are demanding that all investors in Ajnara Ambrosia should withdraw their amount given to the builder and now after 5-6 months they will sell the same inventory at the rate of RS 4500-5000 per sq ft.............I might be wrong but something is fishy with Ajnara Ambrosia now........I have come to known that Ajnara is scrapping this project due to land problems.......But how can such reputed builder do this ??? Either this is game played by the builder or some consortium........Any inside story Please or comment ?? I have also invested in this project in last May 2012....There is hardly any response from the Ajnara office...
Hi, Many projects in Noida come in NGT (National Green tribunal) and construction has been stopped. Can anybody has idea which all projects are in this ruling, or is any threat on Ambrosia as well?Hi, Many projects in Noida come in NGT (National Green tribunal) and construction has been stopped. Can anybody has idea which all projects are in this ruling, or is any threat on Ambrosia as well?
http://ravikanthpropertyconsultant.wordpress.com/2014/06/14/no-136-100000-flats-investors-affected-ngt-stop-construction-order-okhla-bird-sanctuary-national-board-of-wild-life-saga-in-noida/
Though currently Sector 118 is not in the list, but sector 137 project of Ajnara is affected.http://ravikanthpropertyconsultant.wordpress.com/2014/06/14/no-136-100000-flats-investors-affected-ngt-stop-construction-order-okhla-bird-sanctuary-national-board-of-wild-life-saga-in-noida/
Though currently Sector 118 is not in the list, but sector 137 project of Ajnara is affected.
My comments to replies
Anyone who has booked in Tower E in this forum?
I have booked in Tower E...Is there any issue with this tower?
20th August 2014
Hi All,
I spoke to Lalit Tyagi, marketing manager ajanara ambrosia, today. He said that launch for this project is delayed till Diwali. He also said that farmers are creating trouble in noida. ajanara is about to settle issue with them. However, he cannot give any deadline for launch..
Hey guys my name is Vinay. I have also booked one unit in Ajnara Ambrosia. I have spoken to Lalit and he said till Diwali nothing will be done in this project but he didn't give assurance that after diwali it will launch for sure. This is biggest mistake of my life to chose Ajnara. Now i want to quit from this project and searching another property.
25th July 2013
Hello Group Members,
I have got demand letter for casting of 6th floor in Tower H (due day 26th July) and again in a span of 1 month I got another demand letter for casting of 12th floor in Tower H.
I was amazed that how is it possible to cast 6 floors in 1 month ? Did some one get same type of demand letter.
I called Dimple and she told me that she did not visited the construction site so she is not able to comment on this. She just got data, based on which she issued the demand letter.
Further she said that I can confirm myself by visiting the construction site.
Please share your thoughts on the same.
Yes construction in good pace, in almost 15 days builder complete 1 floor. The issue is till 18th floor builder will demand 85% payment and after that you will see slower pace in construction. As per BBA completion date is August 17. So after paying 85% you have to wait for at least 2 years to get your flat.
3rd September 2015