Q: I have booked a flat in LDA srishti apartment flat Kursi rd scheme 3 years back. Can any one please tell me what is the status of project. LDA people even do not pick the phone.

My comments to replies
Dear All, following are the details which My Brother in Law received in written, now add + 6 month at max in this optimistically Srishti Aprtment will be delivered and opened for registration in the month of january 2015.
Hi Rakesh, Once LDA wil start registration how they will inform us?
30th October 2014

Continuing my last comment, Following are the steps: 1. Keep writing weekly mail to LDA official about status, and remuneration for delayed project. 2. We will write emails to Chief minister and secretary also. These two activities for next 2 months. 3. After that a simple case can be filed based on letters, emails etc. Any other suggestions welcomed.
Hi , I am Abhishek...I visited the site on 19th'Dec,2015. As per my understanding the E& F and buildings are almost done. In building D still interior work is going on. The way work is going on...overall it will take another 6-month.. I have taken few snaps if any one want please share your e-mailds. Regards Abhishek
22nd December 2015
Hi Rajesh and Anurag, I have shared snaps with you...please check your e-mail. Regards Abhishek
28th December 2015