mahesh, Navi Mumbai
Q: Neel Sidhi Amarante is yet to get electricity connection from MSEB. It's been heard that MSEB doesn't have sufficient infrastructure(Feeder transformers & lines) to feed approx. 1000 flats in this project. So any idea, what's the status of electricity connection issue?

My replies to this discussion
Hi guys, This is Mahesh Darade, flat no 303, bldg -10. Its really frustrating, builder doesnt have any proper answer & every time they just say it will be done in 1-2 months. I am getting this response since last year. Hope with high court order, MSEB will follow the 3 months time period. I got to know last week that MSEB has opened tender for the work to be completed...lets hope for the best My contact no. 9594037020. if you have any updates further please let me knowHi guys, This is Mahesh Darade, flat no 303, bldg -10. Its really frustrating, builder doesnt have any proper answer & every time they just say it will be done in 1-2 months. I am getting this response since last year. Hope with high court order, MSEB will follow the 3 months time period. I got to know last week that MSEB has opened tender for the work to be completed...lets hope for the best My contact no. 9594037020. if you have any updates further please let me know
Ask a Question
120 Characters Left





    Trending Categories

    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!