Q: I need feedback on NSD builders, can anyone help me? Planning to buy a home at Sonesta Meadows, Thubarahalli, Bangalore. Is it worth to buy?
My replies to this discussion
The project is 3 years delayed and still not complete. The approach road is in dispute. The builder told me that the road is starting next month 2 years back . Still you will get the same reply. (Builder cheated saying its 40ft. Now its only 8 ft)The project is 3 years delayed and still not complete. The approach road is in dispute. The builder told me that the road is starting next month 2 years back . Still you will get the same reply. (Builder cheated saying its 40ft. Now its only 8 ft)