Latest Answer: Thanks.
It would be great if we get possession in 2014.
My flat in Bldg 8 is in the same status more than 1 year so really doubt if they will be able to give possession by 2014. Let us hope for the best. :)
Q:
I received latest architect certificate.
I found progress quite satisfactory.
I have apartments in Bldg 8.
Bldg Floors
4,6,9,10,14,24,29,30 Plinth
11,12,15,18,21,23,27 1
22 2
1 4
2 7
17 14
28 15
20 17
3,7,8,16 Terrace
I spoke to site office today and he said for 9 bldgs they will give possession by Dec, 2013.
It is wise decision by DB they give phased possession.
Latest Answer: kuch nahin hoga .....our agreement states 2015....so we cant do anythin before that .....same story everywhere delay delay delay ...................tarrek pe tareek , tareek pe tareek , tareek pe tareek
Latest Answer: Even if we get possession by 2014, it is ok, at least our money is secured. But the way DB group is being treated in this 2G scam, I doubt, if company will be able to sustain. :(