Hi Venkat - please join other owners at the below group and lets discuss next steps on the reckless delays by Mantri.
https://groups.google.com/d/forum/mantricelestiaowners Hi Venkat - please join other owners at the below group and lets discuss next steps on the reckless delays by Mantri.
https://groups.google.com/d/forum/mantricelestiaowners
Q:
Agreement was done with a hope of having shelter and put stop to rent burden. Finally after paying 95% of flat cost they said possession would be delayed by 12 months. customer is overburdened with an EMI as well as with a huge rents. There is no any proper response from builder side about compensation.
Is builder ready for registration of our flats? Is any one got it done? Kindly advice.
Mantri has been taking all of us who put our trust in them for granted. I have created a group email - dedicated only for genuine owners of Mantri Celestia properties. I hope that we can all get together on this and take up our concerns around the continuous delays with the Celestia project with the Mantri Management. And hopefully if presented by a collective group, our concerns will be taken more seriously and by people who are more responsible and serious about customer commitments.Mantri has been taking all of us who put our trust in them for granted. I have created a group email - dedicated only for genuine owners of Mantri Celestia properties. I hope that we can all get together on this and take up our concerns around the continuous delays with the Celestia project with the Mantri Management. And hopefully if presented by a collective group, our concerns will be taken more seriously and by people who are more responsible and serious about customer commitments.
My comments to replies
Mantri has been taking all of us who put our trust in them for granted. I have created a group email - dedicated only for genuine owners of Mantri Celestia properties. I hope that we can all get together on this and take up our concerns around the continuous delays with the Celestia project with the Mantri Management. And hopefully if presented by a collective group, our concerns will be taken more seriously and by people who are more responsible and serious about customer commitments.
If you are a Mantri Celestia owner and are as frustrated and concerned about the continuous delays with the project - please join the below group. Please note that in order to focus on our plight as owners - this group shall solely focus on the concerns of the owners of Celestia. This group is not intended for new buyers or potential interested parties or brokers favoring Mantri. This group will be solely for the purpose of getting all the owners of Celestia together and driving a strong message to Mantri management as well as to explore any legal avenues against Mantri if they continue to play deaf to our sincere pleas and concerns.
Please join at:
https://groups.google.com/d/forum/mantricelestiaowners
13th January 2013
I think demanding financial compensation from Mantri Celestia is the way forward to go, for the delay , jointly by the owners of flats.
I agree with Appaji. Having seen pathetic responses from the 1st level staff and their managers at the Wipro Junction office - I am willing to join interested flat owners and move forward with either a legal recourse or reaching out to senior Mantri management as ONE voice. Not trusting the commonfloor owenrs group - I have created a gmail group to discuss this further. Please feel free to join yourself into that group if you feel the same way and discuss this further.
https://groups.google.com/d/forum/mantricelestiaowners
Q:
We have booked a flat with Mantri Celestia over 2.5 yrs ago. The flat was part of Phase 1 and was supposed to be handed over in Dec 2011. After having done 90% of the payment by Oct 2011 itself, only in Dec 2011, they inform us about a delay of 12 mth & inform a possession date by Dec 2012.
Now in Dec 2012, they are again pushing the possession by 3 mths(and I definately cant trust them).
What I want to highlight is the unprofessionalism from a builder of such high repute. They have no regrets and no penalty for delay). Also, this year, only when we called up to check status in Dec 2012, they are informing us a further delay (and all was on schedule until 2 months ago).
One critical thing I would like to highlight is that while 90% of work was completed in oct 2011 last year, instead of working on completing the rest of the work, they have invested their resources in bringing up the commercial block
I am looking for owners who have invested in Mantri Celestia (HYD) project and we really need to join hands against the builder to raise our voices. I have been very vocal about the issues but I don’t see any response from the management team on this. Srinivas Manda, the head for this project here, is of no use as he has no controls / inputs. No mgmt. representative is willing to face the customers and the poor Customer Relation Executive is the one taking all the bashing for no fault of hers.Only reason we had invested into the premium project (we had shelled 3190/sft when other projects were willing to negotiate for 2300/2500 / sft at those times) was the brand credibility. If that is only not there, the premium is definitely not worth it. I’m willing to go to consumer court or legal in order to ensure a penalty / ownership by the builder / management. If you / anyone you know has invested in Mantri Celestia Please reach out and we can take this forward together.
Like Rachna, I booked the flats in late 2009 and had made 95% of the payments as per their payment plan - even in Nov 2011 I was told that the handover would happen in Dec 2011. In Dec 2011 I was told its being delayed till Dec 2012 but they were still encouraging us to pay off the remaining amounts (sic!). In Dec 2012 (letter dated 26th) we were informed by snail mail (that reached us first week of Jan) that the handover has been further delayed until Sep 2013. And I am very confident given the increasing notorious and fraudulent reputation of Mantri that the last week of Sept 2013 I will hear that the handover has been delayed again!!
I would like to get all of the owners together and make Mantri accountable and and stop taking the owners for granted - no more verbal sweet talk from underlings who have no say in the decision making process of Mantri Celestia.
Please join:
https://groups.google.com/d/forum/mantricelestiaowners
or mailto: mantricelestiaowners@googlegroups.comLike Rachna, I booked the flats in late 2009 and had made 95% of the payments as per their payment plan - even in Nov 2011 I was told that the handover would happen in Dec 2011. In Dec 2011 I was told its being delayed till Dec 2012 but they were still encouraging us to pay off the remaining amounts (sic!). In Dec 2012 (letter dated 26th) we were informed by snail mail (that reached us first week of Jan) that the handover has been further delayed until Sep 2013. And I am very confident given the increasing notorious and fraudulent reputation of Mantri that the last week of Sept 2013 I will hear that the handover has been delayed again!!
I would like to get all of the owners together and make Mantri accountable and and stop taking the owners for granted - no more verbal sweet talk from underlings who have no say in the decision making process of Mantri Celestia.
Please join:
https://groups.google.com/d/forum/mantricelestiaowners