Hi Guys, Last Saturday on 20th February, 2016 i Visit to Dream Valley site. The total work of construction is stopped due to non-Sufficient funds with Amrapali group. I asked the Contractor person why has been stopped the work? They told me Last 3 to 4 months the work has stooped because the Builder neither paid the money (Payment to Contractor) to us last 6 months and nor they provide material for making Tower (Shortage of Material due to Non-Sufficient funds with Amrapali Group). all Towers are in Uncompleted condition. The Amrapali guys said the we shell provide Possession till Dec., 2017.
We request to all flat buyer please ask to Amrapali Group CMD Dr. Anil Kumar Sharma when will he provide Possession to us our Dream flat? I am also a flat buyer in block B.
Prem, Delhi
Hi all Guys,its true Dream Valley site the total work of construction is stopped. as per current construction status that is not possible of provide Possession till Dec., 2017.
Regards