Latest Answer: P.residency upto 5 building possession started,p.exotica c,d,e, wing basement 2 nd slab work going on.they say in 2 yrs they wil give exotica possession,kohinoor chs going on price is 15k, p.residency 1 bhk available on resale basis. As on 23-9-13
Q:
I had receive a demand note for the plinth + Vat + Services Tax dues. I thank many other buyer might have receive the same. Can we all buyers have a joint meeting with builder on some Sunday to understand the future progress of work? After making the payment we may stuck with PreEMI liability for a stopped work.
Latest Answer: Hi, i suggest we all should go and meet the bulider. Even i have my initial payment stuck and there is no sign on the progress of the construction
Q:
I have few photo of ongoing work at Exotica Site. The phase I (Premier Residence) Will be given possession In Dec 2012. At present Finishing work is in progress( Tile,Plumbing. Elect Etc).
Latest Answer: good news...good news....today i visited the site.work has started 4 days back ..jaysukh patel is the new contractor for premier exotica.at present they have started work on A AND B WING..excavation for other wings has also started.around 100 workers were at the site.hope the work goes on till the project gets completed.
regards,
someshwar
Q:
The work is in full swing at premier exotica site. Builder had created a new entrance just opposite Don Bosco Collage which directly lead to premier exotica Building-3. Builder had put a stall at site to entertain buyers. He is getting many new inquiry as seen by crowd. The Quoted rate is Rs 9450/_ psf which he intended to hike soon. Few 1 BHK of Area 792 and 826 are also available. Builder Procession date is in Dec 2013. The work is also going in SRA Site and Premier Residence. I also have few photo of site but this site do not have photo upload facility.
Latest Answer: the builder has again hiked the rate per sq,ft for exotica.the latest rate is rs 12500 per sq,ft..transfer charges too hiked again..its rs 1000 per sq,ft..parking charges hiked too by rs 2 lakh per parking lot..
Q:
The Premier Exotica Adv appear edin today's Times of India(11/08/12). Builder offers a rate of about 9000/- per sqft with special rate for first 50 flats. It appears that builder wants to gain speed in construction by selling remaining unsold flats.
Q:
I had gone to site on Sunday 22/07/12 at 11 am. About 10 workers are working on Exotica site Bulding 3, and few about 15 on site building 4. The plastering work is undergoing at SRA site and Tile work is going at Phase I Premier Residence . You can visit and see yourself. The work is slow and Mr Vinay is right, this will take another 2-4 years to complete Phase II.
Q:
The work is restarted after a gap of one year. Work is restarted in all the sections Phase I , II and SRA section. In Phase II (Exotica) 3 buildings are being constucted.
Latest Answer: Hi All, I m about to file a case against HDIL for delay of construction. please call me in case any one of u all are interested - 9870240910